Annanagar Library Construction July-Aug 2018

In July/August 2018 : Hyundai Glovis sponsored library construction at Annanagar continues in July and August of 2018. Building is structurally complete.

The construction of the library at Annanagar slowed down during these two months because of delay in getting the doors and windows etc. At the end of August the building was structurally complete. Plastering, fall for the roof, corridor, doors/windows etc. were all completed.

Click here to see the photos from the work in July/August.